Sample Test Plan

Chapter 5 - Resources


5. RESOURCES

5.1. Human

 

Resource Type 

Resource Title 

No. 

Date Req'd 

Who 

Status 

           
Project Mgmt/Functional  Business Analyst   1  A.N. Other  Assigned 
           
Testing  Test Controller   1   - A. Smith  Assigned 
  Testers   4   1st May   To Be Assigned 
           
Test Support Team  Support Programmers   4  15th May   To be Assigned 
  Technical Support   1  1st May   To be Assigned 
  WAN Support   1  25th May   To be Assigned 
           
Technical - External  CIS Support  1  25th May   To be Assigned 
  Bookkeeping Support   1  15th May   To be Assigned 
  External Liaison Support   1  25th May C. Jones Assigned
           
Business  Business Expert/ 
Business Representative 
 1  1st May   To be Assigned 
           
 

5.2. Hardware

One seperate, controlled system will be required for the initial phase
of testing, setup as per one standard, complete office environment.
In order to maintain the integrity of the test environment his network
will not be accessible to anybody outside this project. The printers are
also exclusively for use by the test network.

Hardware components required

  • 1 Network Controller
  • 6 Networked PC's (See below)
  • 1 DAP Workstation
  • 1 Motorola 6520
  • 1 Alpha AXP Server
  • 1 Batch Waste Printer
  • 1 HP LaserJet 4v Printer

PC Specifications
            The 6 PC's required for the test environment will include the following:
            1 x P100, 1Gb HD, 16Mb RAM [Current Minimum Specification]
            3 x P166, 1.5Gb HD, 32Mb RAM [Current Standard Specification]
            1 x P333, 2.5Gb HD, 64Mb RAM [Current Maximum Specification]

These specifications are the various specifications currently in use in different branches.

1 x Pentium running Windows NT is also required as the Test center for controlling and executing the automated testing.

5.3. Software

Test IMS environments

Test IMS region X will be required for System Testing. Additional or amended
data will be populated where required.

Test Environment Software

System Test will be run on the following Software Versions :-
            Custom Destop Vers.97.0.1
            Windows 95 Operating System
            Visual Basic 5 Runtime Files
            MS Office 97
            Novell Netware

Error Measurement System

This system test will use a bespoke MS Access database Error Management system.
A new database will be implemented for the sole use of this project.
[See Chapter x ]